PROCEDURES PRIOR TO ARRIVAL OF HKS VENEZUELA EQUIPMENT & CREW
  • Furnace is shutdown, de-pressured and blanked.
  • Hydrocarbons are removed from heater tubes by steaming or flushing.
  • Process piping is unhooked and removed to prepare for pigging - 300 rf Flanges.
  • It is preferred, but not mandatory, that inlets and outlets of each pass be piped to grade (ground level) to ensure safety. Depending on the size of launcher/receivers used, the space required to install and operate is approximately 1.2m x 2.4m. (4ft. x 8ft.). Minimum overhead clearance required is 2 meters (7 ft).
  • All thermo wells must be removed.
  • It’s with a similar size to the clean I.D. of the heater tubes to be cleaned may require a blind flange with insert. The issue of any steam injection lines, valves, etc., which may interfere with the travel of the pig will be discussed and addressed prior to job commencement.
  • The transition from HKS Pigging Systems’ Ball Valve Launcher/ Receiver to the Refinery’s supplied 300 rf flange piped to the heater inlets and outlets must be smooth.