|
|
Phase
1. Arrival:Upon arrival, the trailer mounted Pumping Unit will be spotted in a position agreed to with Refinery Management. Dimensions of the Pumping Unit: -48' long -13'6" high -8'.6 wide When the technicians have been cleared through site specific, hook-up to the furnace will begin. The Unit arrives with all required equipment, including launchers, rigid & flexible 3" water piping complete with a comprehensive variety of couplings. |
|
|||||||||||||||||||

Phase
2. Furnace Hook-up:During the set-up procedure, connection is made to a pair of passes (coils) with flow & return piping; there are four separate piping links between the furnace and the Double Pumping Unit. 300# flanges at all pass access points require to be cleared for the connection of the special launcher/receiver units. These are always set horizontally. Launcher/receivers are complete with a full port ball valve and may require a refinery supplied crane to lift into position. The launcher/receiver must be positioned to be safely accessible and the end access doors can be freely operated. It is not mandatory for the launcher/receivers to be at grade however such an arrangement is usually safer and can also facilitate a smoother & quicker hook-up. On each launcher/receiver is a hammerlock coupling for attaching the water piping. This piping, maybe flexible and or rigid, and will run horizontally & Double Pumping Unit. |
|
|||||||||||||||||||
| Phase 3. Utilities: a.-electricity: Two 20 amp - 110v HKV circuits will be connected to a locally available electrical outlet. This is preferred as 'clean' power for operating the onboard computerized tracking systems. b.-fuel: Diesel fuel to be supplied by the Refinery as required. c.-water: A connection is required from a nearby refinery fire hydrant. |
|
|||||||||||||||||||||||||||
|
Phase 4. The pigging operation: A full port ball valve separates each launcher/receiver from the passes. By the operation of these valves the launcher/receivers can be isolated from the system for the loading, recovery and changing of pigs. Once the furnace tubes are filled, the technicians circulate water only, for the purpose of removing remaining hydrocarbons and loose debris. The decoking process starts with a foam pig launched into a pass and propelled through, to be received at the corresponding pass outlet and or inlet. After inspecting the condition of the recovered special density foam pig, a decoke pig is selected and launched to clean a chosen diameter of the tubing within that pass or coil. During the procedure the pigs are increased in size incrementally and
different types of the 'family' of 'HKS' pigs may be selected. The
specialized experience and continuous intense training of the technicians
is a key factor within the core of the process. Before the technicians
can confirm the completion of cleaning in a chosen pass, an oversized
pig is used in an effort to compensate for any distortion or ovality which
may exist in the furnace tube after previous uses of steam air decoking.
The final runs in any given pass are made using an oversize 'silica' type
abrasive coated foam pig for the purpose of polishing away any remaining
isolated patches of coke or inorganic deposits. Upon the completion of a pair of passes or coils which are being simultaneously
decoked, launcher/receivers are uncoupled without delay (crane maybe required).
At this point, passes are drained using a method previously agreed to
with Refinery Engineers. In the case of vertical furnace tubes, a compressed
air purge maybe required to remove all remaining water.
|

|
|||||||||||||||||||||||
| Phase 5. Effluent: During the course of the decoke dirty returns containing coke, hydrocarbons and 'black water' will be received in the Double Pumping Unit's effluent tank. Large sizes of coke and removed contaminants will be held in the stainless steel catch baskets; suspended solids in the form of 'fines' will settle in the effluent tank and will form a sludge in the bottom. As the tank fills during the process, discoloured water will require disposal by the refinery, this is normally done by direct draining into the refinery sewer system or by using a vacuum truck. |
| Phase 6. Completion: At the end of the decoking operation, with all passes/coils cleaned and drained, all equipment is disconnected and mounted back onto the road going Pumping Unit. All equipment and personnel are then removed from site, leaving the area clean and clear. |
|
|||||||||||||||
|